10 Prospect Street (D2.1) – Future Life Sciences Building (closest to Somerville Avenue)
Gilbane Building Company
The following activities are expected to take place:
Steel erection and detailing on the upper floors
Prepare and place the slab on deck on the M1 floor on Thursday 6/23 or Friday 6/24
Mechanical, Electrical, and plumbing rough in
Curtain wall deliveries and installation
Spray fireproofing
Prepare and place the ground floor slab on Wednesday 6/22 or Thursday 6/23
Weekend Work (6/18): Curtain Wall Deliveries or jump man and material hoist
Note: Concrete trucks for slab placement may cause periodic noise and/or vibration.
20-50 Prospect Street (D2.2-D2.3) – Future Apartment Building (closest to MBTA Station)
Cranshaw Construction
The following activities are expected to take place:
Concrete placements at the mid-rise
Steel erection and precast install at the tower & mid-rise
Wood panel erection at the mid-rise
MEP rough at the mid-rise & tower
Masonry shaft block work at the tower & mid-rise
Weekend Work (6/18): Building clean-up & trash removal. MEP rough at the mid-rise & tower.