Planned Activities for the Week of 6/27/2022 - 7/3/2022

10 Prospect Street (D2.1) – Future Life Sciences Building (closest to Somerville Avenue)

Gilbane Building Company

The following activities are expected to take place:

  • Steel detailing on the upper floors

  • Mechanical, Electrical, and plumbing rough in

  • Curtain wall deliveries and installation

  • Spray fireproofing

  • Prepare and place the ground floor slab on Wednesday 6/29

Weekend Work (6/25): No Saturday Work
Note: Concrete trucks for slab placement may cause periodic noise and/or vibration.

20-50 Prospect Street (D2.2-D2.3) – Future Apartment Building (closest to MBTA Station)

Cranshaw Construction

The following activities are expected to take place:

  • Concrete placements at the mid-rise garage

  • Steel erection and precast install at the tower & mid-rise

  • Wood panel erection at the mid-rise

  • MEP rough at the mid-rise & tower

  • Masonry block work at the tower & mid-rise

Weekend Work (6/25): Building clean-up & trash removal. MEP rough & window work

Thank you,

US2
Gilbane Building Company
Cranshaw Construction