Planned Activities for the Week of 6/13/2022 - 6/19/2022

10 Prospect Street (D2.1) – Future Life Sciences Building (closest to Somerville Avenue)

Gilbane Building Company

The following activities are expected to take place:

  • Steel deliveries and detailing

  • Mechanical rough in

  • Underground utilities

  • Curtain wall deliveries

  • Curtain wall prep for installation

  • Spray fire proofing

Weekend Work (6/11): Curtain wall deliveries

20-50 Prospect Street (D2.2-D2.3) – Future Apartment Building (closest to MBTA Station)

Cranshaw Construction

The following activities are expected to take place:

  • Concrete placements at the mid-rise

  • Steel erection and precast install at the tower

  • Wood panel & truss install at the mid-rise

  • MEP work at the mid-rise & tower

  • Masonry shaft block work at the mid-rise & tower

Weekend Work (6/11): Building and site clean-up opeartions & MEP rough at the the tower.

Thank you,

US2
Gilbane Building Company
Cranshaw Construction