Planned Activities for the Week of 5/9/2022 - 5/15/2022
10 Prospect Street (D2.1) – Future Life Sciences Building (closest to Somerville Avenue)
Gilbane Building Company
The following activities are expected to take place:
Steel deliveries and steel erection
Spray Fireproofing
Place 6th floor slab
Underground plumbing and electrical installation
Install man & material hoist
Weekend Work (5/7): Steel Erection.
Note: Concrete deliveries may cause periodic noise and/or vibration. Weather permitting, on Friday we are planning to place the 6th floor slab. This activity will start early at 5 a.m. and will go into the evening.
20-50 Prospect Street (D2.2-D2.3) – Future Apartment Building (closest to MBTA Station)
Cranshaw Construction
The following activities are expected to take place:
Concrete placements at the mid-rise
MBTA elevator and stair work
Steel erection and precast install at the tower
Masonry shaft block work at the tower & mid-rise
Underground utility work in the mid-rise
Site grading at D2.4
Weekend Work (5/7): Mechanical, electrical and plumbing (MEP) work at the tower. Site clean-up and trash removal operations.
Note: Periodic vibratory work at the D2.4 site, adjacent to the Allen Street gate.