Planned Activities for the Week of 5/9/2022 - 5/15/2022

10 Prospect Street (D2.1) – Future Life Sciences Building (closest to Somerville Avenue)

Gilbane Building Company

The following activities are expected to take place:

  • Steel deliveries and steel erection

  • Spray Fireproofing

  • Place 6th floor slab

  • Underground plumbing and electrical installation

  • Install man & material hoist

Weekend Work (5/7): Steel Erection.

Note: Concrete deliveries may cause periodic noise and/or vibration. Weather permitting, on Friday we are planning to place the 6th floor slab. This activity will start early at 5 a.m. and will go into the evening.

20-50 Prospect Street (D2.2-D2.3) – Future Apartment Building (closest to MBTA Station)

Cranshaw Construction

The following activities are expected to take place:

  • Concrete placements at the mid-rise

  • MBTA elevator and stair work

  • Steel erection and precast install at the tower

  • Masonry shaft block work at the tower & mid-rise

  • Underground utility work in the mid-rise

  • Site grading at D2.4

Weekend Work (5/7): Mechanical, electrical and plumbing (MEP) work at the tower. Site clean-up and trash removal operations.

Note: Periodic vibratory work at the D2.4 site, adjacent to the Allen Street gate.

Thank you,

US2
Gilbane Building Company
Cranshaw Construction

Previous
Previous

Planned Activities for the Week of 5/15/2022 - 5/21/2022

Next
Next

Planned Activities for the Week of 5/2/2022 - 5/8/2022