Planned Activities for the Week of 5/2/2022 - 5/8/2022

10 Prospect Street (D2.1) – Future Life Sciences Building (closest to Somerville Avenue)

Gilbane Building Company

The following activities are expected to take place:

  • Steel erection and detailing

  • Steel Deliveries

  • 1st floor underground utility installation and backfill

  • Place 5th floor slab on deck

  • Spray fireproofing

  • Deliver and install man and material hoist

  • Install plumbing risers

Weekend Work (5/1): Steel Erection.

Note: Concrete deliveries may cause periodic noise and/or vibration. Weather permitting, on Thursday we are planning to place the 5th floor slab. This activity will start early at 5 a.m. and will go into the evening

20-50 Prospect Street (D2.2-D2.3) – Future Apartment Building (closest to MBTA Station)

Cranshaw Construction

The following activities are expected to take place:

  • Concrete placements at the mid-rise

  • MBTA elevator & stair work

  • Steel erection and precast install at the tower

  • Masonry shaft block work at the tower & mid-rise

  • Underground utility work in the mid-rise

  • Site grading at D2.4 and remaining utility tie-in work

Weekend Work (5/1): Mechanical, electrical and plumbing (MEP) work at the tower. Site clean-up and trash removal operations.

Note: Adjacent to the Allen Street gate, periodic vibratory work all week.

Thank you,

US2
Gilbane Building Company
Cranshaw Construction