Planned Activities for the Week of 5/15/2022 - 5/21/2022
10 Prospect Street (D2.1) – Future Life Sciences Building (closest to Somerville Avenue)
Gilbane Building Company
The following activities are expected to take place:
Steel erection and deliveries
Curtain wall clips and starter track
Spray Fireproofing
Install man and material hoist
Steam Wall ongoing
Plumbing and HVAC builds off floors
Underground utilities
Weekend Work (5/14): Steel Erection and detailing
Note: Concrete deliveries may cause periodic noise and/or vibration.
20-50 Prospect Street (D2.2-D2.3) – Future Apartment Building (closest to MBTA Station)
Cranshaw Construction
The following activities are expected to take place:
Concrete placements at the mid-rise
MBTA elevator and stair work
Steel erection and precast install at the tower
Wood panel erection at the mid-rise
Masonry shaft block work at the tower & mid-rise
Underground utility work in the mid-rise
Site grading at D2.4 and remaining utility tie-in work
Weekend Work (5/14): Mechanical, electrical and plumbing (MEP) work at the tower. Site clean-up and trash removal operations.
Note: Periodic vibratory work at the D2.4 site, adjacent to the Allen Street gate.
Thank you,
US2
Gilbane Building Company
Cranshaw Construction