Planned Activities for the Week of 5/15/2022 - 5/21/2022

10 Prospect Street (D2.1) – Future Life Sciences Building (closest to Somerville Avenue)

Gilbane Building Company

The following activities are expected to take place:

  • Steel erection and deliveries

  • Curtain wall clips and starter track

  • Spray Fireproofing

  • Install man and material hoist

  • Steam Wall ongoing

  • Plumbing and HVAC builds off floors

  • Underground utilities

Weekend Work (5/14): Steel Erection and detailing

Note: Concrete deliveries may cause periodic noise and/or vibration.

20-50 Prospect Street (D2.2-D2.3) – Future Apartment Building (closest to MBTA Station)

Cranshaw Construction

The following activities are expected to take place:

  • Concrete placements at the mid-rise

  • MBTA elevator and stair work

  • Steel erection and precast install at the tower

  • Wood panel erection at the mid-rise

  • Masonry shaft block work at the tower & mid-rise

  • Underground utility work in the mid-rise

  • Site grading at D2.4 and remaining utility tie-in work

Weekend Work (5/14): Mechanical, electrical and plumbing (MEP) work at the tower. Site clean-up and trash removal operations.

Note: Periodic vibratory work at the D2.4 site, adjacent to the Allen Street gate.

Thank you,

US2
Gilbane Building Company
Cranshaw Construction

Previous
Previous

Planned Activities for the Week of 5/23/2022 - 5/29/2022

Next
Next

Planned Activities for the Week of 5/9/2022 - 5/15/2022