10 Prospect Street (D2.1) – Future Life Sciences Building (closest to Somerville Avenue)
Gilbane Building Company
The following activities are expected to take place:
Steel Erection
Steel deliveries
1st floor underground utilities
Spray fire proofing
Weekend Work (4/23): Mechanical, electrical and plumbing (MEP) work at the tower. Site clean-up and trash removal operations.
Note: Adjacent to the Allen Street gate remaining utility and subgrade work will continue, periodic vibratory work all week.
20-50 Prospect Street (D2.2-D2.3) – Future Apartment Building (closest to MBTA Station)
Cranshaw Construction
The following activities are expected to take place:
Concrete placements at the mid-rise
Steel erection and plank install at the tower
Masonry shaft block work at the tower & mid-rise
Underground utility work in the mid-rise
Site grading at D2.4 & remaining utility tie-in work
Weekend Work (4/23): Site clean-up and trash removal. Tower plumbing and mechanical work.
Note: Adjacent to the Allen Street gate remaining utility and subgrade work will continue, periodic vibratory work all week. Monday, 4/18 will have very limited site activity due to the holiday.
Thank you,
US2
Gilbane Building Company
Cranshaw Construction