Planned Activities for the Week of 4/18/2022 - 4/24/2022
10 Prospect Street (D2.1) – Future Life Sciences Building (closest to Somerville Avenue)
Gilbane Building Company
The following activities are expected to take place:
Steel Deliveries
Steel Erection
Weekend Work (4/16): Saturday may be used to catch up if the project incurs a weather day.
20-50 Prospect Street (D2.2-D2.3) – Future Apartment Building (closest to MBTA Station)
Cranshaw Construction
The following activities are expected to take place:
Concrete placements at the mid-rise
Steel erection and plank install at the tower
Steel & deck detailing at the mid-rise
Masonry shaft block work at the mid-rise & tower
Underground utility work in the mid-rise & tower
Utility and grading work at D2.4.
Weekend Work (4/16): Site clean-up and trash removal. Tower plumbing and mechanical work.
Note: Adjacent to the Allen Street gate remaining utility and subgrade work will continue, periodic vibratory work all week. Monday, 4/18 will have very limited site activity due to the holiday.
Thank you,
US2
Gilbane Building Company
Cranshaw Construction