Planned Activities for the Week of 3/20/2023 - 3/26/2023
10 Prospect Street (D2.1) – Future Life Sciences Building (closest to Somerville Avenue)
Gilbane Building Company
The following activities are expected to take place:
Curtain wall deliveries and installation with crane and a lull
Brick and Masonry walls on the first floor
Interior fit out of the core
Mechanical room fit out
Electrical room rough in
Weekend Work (3/18): Exterior brick piers on the first floor and interior clean-up
20-50 Prospect Street (D2.2-D2.3) – Future Apartment Building (closest to MBTA Station)
Cranshaw Construction
The following activities are expected to take place:
Façade & sealant work at the tower & midrise
Site and hardscape work
MEP rough at the tower & midrise
Interior framing & drywall at the tower & midrise
Interior finishes at the tower & midrise
Roof work at the tower & midrise
Weekend Work (3/18): MEP rough, drywall work and trash removal operations at the midrise & tower
Eversource Neighborhood Infrastructure Project - Work Performed 7PM to 5AM
Update provided by Eversource:
Crews are working to install a distribution manhole (cable vault) and will continue to install distribution conduit in segments within the parcel
As early as Monday, 3/20, crews will begin to excavate across Prospect Street toward the substation. Lane restrictions will be necessary for portions of this anticipated work
Please note, these activities are subject to change due to weather or unexpected circumstances
Work hours remain 7 PM - 5 AM during working days
Residents may reach out to Outreach Specialists Matt Watkins at matthew.watkins@eversource.com or 617-571-4582 and Eric Sacchetti at eric.sacchetti@eversource.com or 781-570-1228 with any questions or concerns.