Planned Activities for the Week of 3/13/2023 - 3/19/2023
10 Prospect Street (D2.1) – Future Life Sciences Building (closest to Somerville Avenue)
Gilbane Building Company
The following activities are expected to take place:
Curtain wall deliveries and installation with crane and a lull
Brick and Masonry walls on the first floor
Interior fit out of the core
Mechanical room fit out
Electrical room rough in
Weekend Work (3/11): Interior cleanup and exterior masonry
20-50 Prospect Street (D2.2-D2.3) – Future Apartment Building (closest to MBTA Station)
Cranshaw Construction
The following activities are expected to take place:
Façade & sealant work at the tower & midrise
Site curb and sidewalk prep. • MEP rough at the tower & midrise
Interior framing & drywall at the tower & midrise
Interior finishes at the tower & midrise
Roof work at the tower & midrise
Weekend Work (3/11): MEP work, interior drywall/finish work and trash removal operations at the midrise and tower.
Eversource Neighborhood Infrastructure Project - Work Performed 7PM to 5AM
Update provided by Eversource:
Crews will continue to install distribution conduit in segments within the parcel
In the coming weeks, crews will begin to excavate and install conduit across Prospect Street toward the substation. Lane restrictions will be necessary for portions of this anticipated work.
Please note, these activities are subject to change due to weather or unexpected circumstances.
Work hours remain 7 PM - 5 AM during working days.
Residents may reach out to Outreach Specialists Matt Watkins at matthew.watkins@eversource.com or 617-571-4582 and Eric Sacchetti at eric.sacchetti@eversource.com or 781-570-1228 with any questions or concerns.