Planned Activities for the Week of 3/6/2023 - 3/12/2023
10 Prospect Street (D2.1) – Future Life Sciences Building (closest to Somerville Avenue)
Gilbane Building Company
The following activities are expected to take place:
Curtain wall deliveries and installation with crane and a lull
Brick and Masonry walls on the first floor
Interior fit out of the core
Mechanical room fit out
Electrical room rough in
Weekend Work (3/4): Interior mechanical and electrical work. No crane.
20-50 Prospect Street (D2.2-D2.3) – Future Apartment Building (closest to MBTA Station)
Cranshaw Construction
The following activities are expected to take place:
Façade & sealant work at the tower & midrise
Site curb and infrastructure work
MEP rough at the tower & midrise
Interior framing & drywall at the tower & midrise
Interior finishes at the tower & midrise
Roof work at the tower & midrise
Note: Construction hoist removal will continue along the west elevation, inside the site limits
Weekend Work (3/4): Site snow removal operations. Interior MEP, drywall & trash removal operations at the tower & midrise.
Eversource Neighborhood Infrastructure Project - Work Performed 7PM to 5AM
Update provided by Eversource:
Crews will continue to install distribution conduit in segments within the parcel.
Please note, these activities are subject to change due to weather or unexpected circumstances.
Work hours remain 7 PM - 5 AM during working days.
Residents may reach out to Outreach Specialists Matt Watkins at matthew.watkins@eversource.com or 617-571-4582 and Eric Sacchetti at eric.sacchetti@eversource.com or 781-570-1228 with any questions or concerns.