Planned Activities for the Week of 2/6/2023 - 2/12/2023
10 Prospect Street (D2.1) – Future Life Sciences Building (closest to Somerville Avenue)
Gilbane Building Company
The following activities are expected to take place:
Curtain wall deliveries and installation with a crane and a lull
Masonry walls on the first floor
Interior fit out of the core
Mechanical room fit out
Electrical room rough in
Weekend Work (2/4): interior electrical work and cleanup
20-50 Prospect Street (D2.2-D2.3) – Future Apartment Building (closest to MBTA Station)
Cranshaw Construction
The following activities are expected to take place:
Façade & sealant work at the tower & midrise
MEP rough at the tower & midrise
Interior framing & drywall at the tower & midrise
Interior finishes at the tower & midrise
Roof work at the tower & midrise
Precast install at the tower's material hoist bay
Note: Construction hoist removal will continue along the west elevation, inside the site limits.
Weekend Work (2/4): MEP rough, framing & drywall & trash removal operations at the tower & midrise
Eversource Neighborhood Infrastructure Project - Work Performed 7PM to 5AM
Update provided by Eversource:
Eversource approved contractors will continue to perform construction activities within the parcel.
Crews will perform construction related to the testing and relocation of water main infrastructure. Residents should not expect an interruption to their water service.
Work hours remain 7 PM - 5 AM during working days.
Residents may reach out to Outreach Specialists Matt Watkins at matthew.watkins@eversource.com or 617-571-4582 and Eric Sacchetti at eric.sacchetti@eversource.com or 781-570-1228 with any questions or concerns.