Planned Activities for the Week of 2/13/2023 - 2/19/2023

10 Prospect Street (D2.1) – Future Life Sciences Building (closest to Somerville Avenue)
Gilbane Building Company
The following activities are expected to take place:

  • Curtain wall deliveries and installation with a crane and a lull

  • Brick and Masonry walls on the first floor

  • Interior fit out of the core

  • Mechanical room fit out

  • Electrical room rough in

Weekend Work (2/11): Curtain wall installation and interior mechanical and electrical work. No crane


20-50 Prospect Street (D2.2-D2.3) – Future Apartment Building (closest to MBTA Station)
Cranshaw Construction
The following activities are expected to take place:

  • Façade & sealant work at the tower & midrise

  • Precast install at the podium

  • MEP rough at the tower & midrise

  • Interior framing & drywall at the tower & midrise

  • Interior finishes at the tower & midrise

  • Roof work at the tower & midrise

Note: Construction hoist removal will continue along the west elevation, inside the site limits.

Weekend Work (2/11): MEP rough, Drywall install & trash removal at the midrise and tower.

Eversource Neighborhood Infrastructure Project - Work Performed 7PM to 5AM
Update provided by Eversource: 

  • Eversource approved contractors will continue to perform construction activities within the parcel, including distribution conduit installation

  • No backfill, or excavation is scheduled for this week

  • Please note, these activities are subject to change as construction activities continue

  • Work hours remain 7 PM - 5 AM during working days

Residents may reach out to Outreach Specialists Matt Watkins at matthew.watkins@eversource.com or 617-571-4582 and Eric Sacchetti at eric.sacchetti@eversource.com or 781-570-1228 with any questions or concerns.

Previous
Previous

Planned Activities for the Week of 2/20/2023 - 2/26/2023

Next
Next

Planned Activities for the Week of 2/6/2023 - 2/12/2023