10 Prospect Street (D2.1) – Future Life Sciences Building (closest to Somerville Avenue)
Gilbane Building Company
The following activities are expected to take place:

  • Somerville Ave Sidewalk installation

  • Curtain wall deliveries and installation with a crane and a lull

  • Masonry walls on the first floor

  • Interior fit out of the core

  • Mechanical room fit out

  • Electrical room rough in

Weekend Work (1/28): Curtain wall installation, roofing, and interior fit-out


20-50 Prospect Street (D2.2-D2.3) – Future Apartment Building (closest to MBTA Station)
Cranshaw Construction
The following activities are expected to take place:

  • Façade & sealant work at the tower & midrise

  • MEP rough at the tower & midrise

  • Interior framing & drywall at the tower & midrise

  • Interior finishes at the tower & midrise

  • Roof work at the tower & midrise

  • Construction hoist removal at the tower

Note: Construction hoist removal will continue along the west elevation, inside the site limits.

Weekend Work (1/28): MEP rough, drywall work, facade sealant work & trash removal at the midrise & tower. 

Eversource Neighborhood Infrastructure Project - Work Performed 7PM to 5AM
Update provided by Eversource: 

  • Eversource approved contractors will continue to perform construction activities within the parcel.

  • Crews will perform construction related to the testing and relocation of water main infrastructure. Residents should not expect an interruption to their water service.

  • Work hours remain 7 PM - 5 AM during working days.

Residents may reach out to Outreach Specialist Matt Watkins at matthew.watkins@eversource.com or 617-571-4582 with any questions or concerns.