Planned Activities for the Week of 2/20/2023 - 2/26/2023
10 Prospect Street (D2.1) – Future Life Sciences Building (closest to Somerville Avenue)
Gilbane Building Company
The following activities are expected to take place:
Curtain wall deliveries and installation with crane and a lull
Brick and Masonry walls on the first floor
Interior fit out of the core
Mechanical room fit out
Electrical room rough in
Weekend Work (2/18): Curtain wall installation and interior mechanical and electrical work. No crane
20-50 Prospect Street (D2.2-D2.3) – Future Apartment Building (closest to MBTA Station)
Cranshaw Construction
The following activities are expected to take place:
• Façade & sealant work at the tower & midrise
Precast work at the tower & podium
MEP rough at the tower & midrise
Interior framing & drywall at the tower & midrise
Interior finishes at the tower & midrise
Roof work at the tower & midrise
Note: Construction hoist removal will continue along the west elevation, inside the site limits
Weekend Work (2/18): MEP rough, drywall work & trash removal at the tower & midrise
Eversource Neighborhood Infrastructure Project - Work Performed 7PM to 5AM
Update provided by Eversource:
There will be no work Monday, February 20, in observance of the holiday.
Eversource approved contractors will continue to install distribution conduit within the parcel.
Crews will backfill a section of recently installed pipe and begin to excavate the next segment.
Please note, these activities are subject to change due to weather or unexpected circumstances.
Work hours remain 7 PM - 5 AM during working days.
Residents may reach out to Outreach Specialists Matt Watkins at matthew.watkins@eversource.com or 617-571-4582 and Eric Sacchetti at eric.sacchetti@eversource.com or 781-570-1228 with any questions or concerns.