10 Prospect Street (D2.1) – Future Life Sciences Building (closest to Somerville Avenue)
Gilbane Building Company
The following activities are expected to take place:

  • Somerville Ave Sidewalk installation

  • Curtain wall deliveries and installation

  • Masonry walls on the first floor

  • Elevator installation

  • Interior fit out of the core

  • Mechanical room fit out

  • Electrical room rough in

Weekend Work (10/22): Curtain wall installation team will be working.

20-50 Prospect Street (D2.2-D2.3) – Future Apartment Building (closest to MBTA Station)
Cranshaw Construction
The following activities are expected to take place:

  • Façade & sealant work at the tower & midrise

  • Wood panel erection at the midrise

  • MEP rough at the tower & midrise

  • Interior framing & drywall at the tower & midrise

  • Finish work at the tower

  • Roof work at the tower & midrise

  • Masonry shaft block work at the garage

  • Tower crane removal