Planned Activities for the Week of 10/31/2022 - 11/6/2022

10 Prospect Street (D2.1) – Future Life Sciences Building (closest to Somerville Avenue)
Gilbane Building Company
The following activities are expected to take place:

  • Somerville Ave Sidewalk installation

  • Curtain wall deliveries and installation

  • Masonry walls on the first floor

  • Elevator installation

  • Interior fit out of the core

  • Mechanical room fit out

  • Electrical room rough in

  • Eversource install main electrical room switchgear

  • Slab on grade placement

Weekend Work (10/29): Curtain wall installation team will be working.
Note: Concrete deliveries may cause periodic noise and/or vibration.

20-50 Prospect Street (D2.2-D2.3) – Future Apartment Building (closest to MBTA Station)
Cranshaw Construction
The following activities are expected to take place:

  • Façade & sealant work at the tower & midrise

  • Wood panel erection at the midrise

  • MEP rough at the tower & midrise

  • Interior framing & drywall at the tower & midrise

  • Finish work at the tower

  • Roof work at the tower & midrise

  • Masonry shaft block work at the garage

Weekend Work (10/29): Tower crane removal operation is to conclude. Tower & Midrise trash removal, roofing, MEP rough & facade work will continue.
Note: Prospect Street closure is tentatively scheduled to be lifted Saturday, 10/29, early evening.

Previous
Previous

Planned Activities for the Week of 11/7/2022 - 11/13/2022

Next
Next

Planned Activities for the Week of 10/24/2022 - 10/30/2022