Planned Activities for the Week of 9/5/2022 - 9/11/2022
10 Prospect Street (D2.1) – Future Life Sciences Building (closest to Somerville Avenue)
Gilbane Building Company
The following activities are expected to take place:
Steel Detailing
Masonry walls on the 1st floor
Misc Concrete placements
Prep and install curtain wall on the 3rd floor
Roofing
Interior shaft and riser work
Penthouse mechanical room rough in
Note: The site will be closed Saturday, 9/3 through Monday, 9/5 for the holiday weekend.
20-50 Prospect Street (D2.2-D2.3) – Future Apartment Building (closest to MBTA Station)
Cranshaw Construction
The following activities are expected to take place:
Concrete placements at the tower
Precast install at the tower & midrise
Wood panel erection at the midrise
MEP rough at the tower & midrise
Interior framing & drywall at the tower & midrise
Masonry shaft block work at the tower & midrise
Note: The site will be closed Saturday, 9/3 through Monday, 9/5 for the holiday weekend.