10 Prospect Street (D2.1) – Future Life Sciences Building (closest to Somerville Avenue)
Gilbane Building Company
The following activities are expected to take place:
Curtain wall deliveries and installation
Masonry walls on the first floor
Elevator installation
Interior fit out of the core
Mechanical room fit out
Electrical room rough in
Weekend Work (9/24): Curtain wall installation
Note: Crane removal from the site will occur next week, likely from Monday (9/26) through Wednesday (9/28), weather dependent. Prospect St will be closed from Somerville Ave to Webster St. A police detail will be present to assist traffic. Pedestrians will have access to Green Line station. For more information view our Transportation Management Plan.
20-50 Prospect Street (D2.2-D2.3) – Future Apartment Building (closest to MBTA Station)
Cranshaw Construction
The following activities are expected to take place:
Site work at the SW corner of the site
Precast detailing at the tower & midrise
Wood panel erection at the midrise
MEP rough at the tower & midrise
Interior framing & drywall at the tower & midrise
Masonry shaft block work at the garage
Weekend Work (9/24): Trash removal operations & MEP rough at the tower & midrise.