Planned Activities for the Week of 7/18/2022 - 7/24/2022
10 Prospect Street (D2.1) – Future Life Sciences Building (closest to Somerville Avenue)
Gilbane Building Company
The following activities are expected to take place:
Steel Detailing
Place concrete curbs and equipment pads
Place Penthouse Mezzanine slab
Spray Fire Proofing
Install block walls on the ground floor
Curtain wall prep and installation
Rough in interior shafts and restrooms
Rough in penthouse and ground floor mechanicals
Weekend Work (7/16): Install Curtain Wall
Note: Concrete deliveries may cause periodic noise and/or vibration.
20-50 Prospect Street (D2.2-D2.3) – Future Apartment Building (closest to MBTA Station)
Cranshaw Construction
The following activities are expected to take place:
Concrete placements at the tower penthouse
Steel erection and precast install at the tower & mid-rise
Wood panel erection at the mid-rise
MEP rough at the mid-rise & tower
Interior framing at the tower & mid-rise
Masonry shaft block work at the tower & mid-rise
Weekend Work (7/16): MEP rough-in at the tower & mid-rise. Steel work at the tower penthouse. Trash removal operations at the tower & mid-rise.
Thank you,
US2
Gilbane Building Company
Cranshaw Construction