Planned Activities for the Week of 5/30/2022 - 6/5/2022

10 Prospect Street (D2.1) – Future Life Sciences Building (closest to Somerville Avenue)

Gilbane Building Company

The following activities are expected to take place:

  • Steel detailing

  • Underground utilities

  • Spray fire proofing

  • Mechanical risers

  • Concrete placement on 7th floor

  • Curtain wall prep

Weekend Work (5/28): Steel Detailing

Note: Concrete deliveries may cause periodic noise and/or vibration.

20-50 Prospect Street (D2.2-D2.3) – Future Apartment Building (closest to MBTA Station)

Cranshaw Construction

The following activities are expected to take place:

  • Concrete placements at the mid-rise

  • Steel erection and precast install at the tower

  • Wood panel erection at the mid-rise

  • Masonry block work at the tower & mid-rise

  • MEP rough at the tower and mid-rise

  • Site grading at D2.4 and remaining utility work

Weekend Work (5/28): Saturday, 5/28 & Monday 5/30 the site will be closed for Memorial Day.

Note: Periodic vibratory subgrade work at the D2.4 site, adjacent to the Allen Street gate.

Thank you,

US2
Gilbane Building Company
Cranshaw Construction