Planned Activities for the Week of 4/4/2022 - 4/10/2022
10 Prospect Street (D2.1) – Future Life Sciences Building (closest to Somerville Avenue)
Gilbane Building Company
The following activities are expected to take place:
Steel Deliveries
Steel Erection
Excavate and install 1st floor underground utilities
Place the 3rd floor slab on deck
Weekend Work (4/2): Saturday may be used to catch up if the project misses a weather day.
Note: Concrete deliveries on Thursday may cause periodic noise and/or vibration. On Thursday we are planning to place concrete on the mezzanine slab on deck.
20-50 Prospect Street (D2.2-D2.3) – Future Apartment Building (closest to MBTA Station)
Cranshaw Construction
The following activities are expected to take place:
Concrete placements at the mid-rise
MBTA elevator work
Steel erection and façade precast install at the tower
Steel & deck detailing at the mid-rise
Masonry shaft block work at the mid-rise
Underground utility work in the mid-rise & tower
Site grading at D2.4
Weekend Work (4/2): Site clean-up and trash removal. Ongoing plumbing work at the tower.
Note: Adjacent to the Allen Street gate will have periodic vibratory work all week.
Thank you,
US2
Gilbane Building Company
Cranshaw Construction