Planned Activities for the Week of 12/19/2022 - 12/25/2022

10 Prospect Street (D2.1) – Future Life Sciences Building (closest to Somerville Avenue)
Gilbane Building Company
The following activities are expected to take place:

  • Somerville Ave Sidewalk installation

  • Curtain wall deliveries and installation with a crane and a lull on the first floor

  • Masonry walls on the first floor

  • Elevator installation

  • Interior fit out of the core

  • Mechanical room fit out

  • Electrical room rough in

Weekend Work (12/17): Curtain wall deliveries and installation with a crane and a lull on the first floor and interior fit out


20-50 Prospect Street (D2.2-D2.3) – Future Apartment Building (closest to MBTA Station)
Cranshaw Construction
The following activities are expected to take place:

  • Façade & sealant work at the tower & midrise

  • Wood frame punchlist work at the midrise

  • MEP rough at the tower & midrise

  • Interior framing & drywall at the tower & midrise

  • Interior finishes at the tower & midrise

  • Roof work at the tower & midrise

  • Masonry shaft block work at the garage

Weekend Work (12/17): Continue MEP rough, framing & trash removal operations at the tower & midrise.  

Eversource Neighborhood Infrastructure Project - Work Performed 7PM to 5AM
Update provided by Eversource: 

  • Beginning on Monday, December 19, Eversource-approved contractors will begin construction activities. On Tuesday, December 20, that will include the start of required excavation work.

  • The week will continue largely with crews dewatering newly dug pits and with valve work.

  • As part of the above, residents can expect crews to utilize requisite equipment to perform these tasks; every effort will be made to attempt to minimize disruption to the local community. Residents can also expect the site to be well-lit during working hours.

  • Work hours will be 7:00 PM - 5:00 AM. Crews will work from Monday - Thursday and will not work the following week. Work at the site will resume on Tuesday, January 3.

For any questions or concerns, residents can reach Keith Sonia, Public Outreach Manager at Eversource. Phone: 781-720-9726; E-Mail: keith.sonia@eversource.com.

Previous
Previous

Planned Activities for the Week of 12/26/2022 - 1/1/2023

Next
Next

Planned Activities for the Week of 12/12/2022 - 12/18/2022