Planned Activities for the Week of 10/10/2022 - 10/16/2022
10 Prospect Street (D2.1) – Future Life Sciences Building (closest to Somerville Avenue)
Gilbane Building Company
The following activities are expected to take place:
Somerville Ave Sidewalk installation
Curtain wall deliveries and installation
Masonry walls on the first floor
Elevator installation
Interior fit out of the core
Mechanical room fit out
Electrical room rough in
Note: There will be no work on the D2.1 project on Saturday 10/8 or Monday 10/10.
20-50 Prospect Street (D2.2-D2.3) – Future Apartment Building (closest to MBTA Station)
Cranshaw Construction
The following activities are expected to take place:
Façade work at the tower & siding prep at the midrise
Wood panel erection at the midrise
MEP rough at the tower & midrise
Interior framing & drywall at the tower & midrise
Unit finish work at the tower
Roof work at the tower and midrise
Masonry shaft block work at the garage
Weekend Work (10/8): Trash removal operations and MEP rough work at the tower & midrise.