Planned Activities for the Week of 7/3/2023 - 7/9/2023

MBTA Updates

  • The MBTA temporary walkway to Union Station, will be removed from service on April 20, 2023 for the construction of the permanent MBTA walkway within the new Civic Plaza

  • The permanent walkway is estimated to complete on July 3, 2023

  • Access to the MBTA Union Station remains available via the Elevator and stairs located on Prospect St

  • Access to Union Station is also available from the east on Charlestown, entrance at Allen St

  • View the proposed TPOT Exhibit here

10 Prospect Street (D2.1) – Future Life Sciences Building (closest to Somerville Avenue)
Gilbane Building Company
The following activities are expected to take place:

  • Roofing - Punchlist

  • Interior fit out of the core - Punchlist

  • Landscape and sitework - Punchlist

Weekend Work (7/1): No work


20-50 Prospect Street (D2.2-D2.3) – Future Apartment Building (closest to MBTA Station)
Cranshaw Construction
The following activities are expected to take place:

  • Façade & sealant work at the tower & midrise

  • Site & hardscape work

  • MEP rough at the tower & midrise

  • Interior framing & drywall at the tower & midrise

  • Interior finishes at the tower & midrise

  • Roof work at the tower & midrise

Weekend Work (7/1):

  • Exterior site

  • Facade and sealant work

  • Interior finish work

  • Trash removal operations at the tower & midrise

Eversource Neighborhood Infrastructure Project - Work Performed 7PM to 5AM
Update provided by Eversource: 

  • Due to the holiday, there will be no project activities on Monday night, July 3, and Tuesday night, July 4.

  • Crews will continue to excavate and install distribution conduit within the parcel between Prospect Street and Allen Street.

  • Please note, construction activities are subject to change due to weather or unexpected circumstances.

  • Work hours remain 7 PM - 5 AM during working days. Some work may be conducted beyond normal work hours with approval from city officials.

Residents may reach out to Outreach Specialists Matt Watkins at matthew.watkins@eversource.com or 617-571-4582 and Eric Sacchetti at eric.sacchetti@eversource.com or 781-570-1228 with any questions or concerns.

Previous
Previous

Planned Activities for the Week of 7/10/2023 - 7/16/2023

Next
Next

Planned Activities for the Week of 6/26/2023 - 7/2/2023