Planned Activities for the Week of 6/5/2023 - 6/11/2023

MBTA Updates

  • The MBTA temporary walkway to Union Station, will be removed from service on April 20, 2023 for the construction of the permanent MBTA walkway within the new Civic Plaza

  • The permanent walkway is estimated to complete on July 3, 2023

  • Access to the MBTA Union Station remains available via the Elevator and stairs located on Prospect St

  • Access to Union Station is also available from the east on Charlestown, entrance at Allen St

  • View the proposed TPOT Exhibit here

10 Prospect Street (D2.1) – Future Life Sciences Building (closest to Somerville Avenue)
Gilbane Building Company
The following activities are expected to take place:

  • Roofing and roof deliveries with a crane

  • Interior fit out of the core

  • Mechanical room fit out

  • Electrical room rough in

  • Landscape and sitework

Weekend Work (6/3):

  • Roofing

  • Interior fit out of the core

  • Mechanical room fit out

  • Electrical room rough in

  • Landscape and sitework


20-50 Prospect Street (D2.2-D2.3) – Future Apartment Building (closest to MBTA Station)
Cranshaw Construction
The following activities are expected to take place:

  • Façade & sealant work at the tower & midrise

  • Site & hardscape work

  • MEP rough at the tower & midrise

  • Interior framing & drywall at the tower & midrise

  • Interior finishes at the tower & midrise

  • Roof work at the tower & midrise

Weekend Work (6/3):

  • Exterior facade & site work

  • Interior finish work

  • Trash removal operations

Eversource Neighborhood Infrastructure Project - Work Performed 7PM to 5AM
Update provided by Eversource: 

  • Crews will continue excavating to install another distribution vault (manhole) within the parcel, between Prospect Street and Allen Street.

  • Please note, construction activities are subject to change due to weather or unexpected circumstances.

  • Work hours remain 7 PM - 5 AM during working days. Some work may be conducted beyond normal work hours with approval from city officials.

Residents may reach out to Outreach Specialists Matt Watkins at matthew.watkins@eversource.com or 617-571-4582 and Eric Sacchetti at eric.sacchetti@eversource.com or 781-570-1228 with any questions or concerns.

Previous
Previous

Planned Activities for the Week of 6/12/2023 - 6/18/2023

Next
Next

Planned Activities for the Week of 5/29/2023 - 6/4/2023