Planned Activities for the Week of 4/17/2023 - 4/23/2023
10 Prospect Street (D2.1) – Future Life Sciences Building (closest to Somerville Avenue)
Gilbane Building Company
The following activities are expected to take place:
Curtain wall deliveries and installation with boom lift and a lull
Brick Piers on the first floor
Roofing and roof deliveries with a crane
Interior fit out of the core
Mechanical room fit out
Electrical room rough in
Landscape and sitework
There will be no work onsite on Monday 4/17 in celebration of Patriots Day
Weekend Work (4/15): Curtain wall installation with a lull and boom lifts and interior mechanical work.
20-50 Prospect Street (D2.2-D2.3) – Future Apartment Building (closest to MBTA Station)
Cranshaw Construction
The following activities are expected to take place:
Façade & sealant work at the tower & midrise
Site & hardscape work
MEP rough at the tower & midrise
Interior framing & drywall at the tower & midrise
Interior finishes at the tower & midrise
Roof work at the tower & midrise
The site will be open for work on Monday, 4/17 with limited activity
Weekend Work (4/15): Facade work, interior MEP & finish work, trash removal operations.
Eversource Neighborhood Infrastructure Project - Work Performed 7PM to 5AM
Update provided by Eversource:
Crews are completing the installation of a second distribution manhole (cable vault) and will continue to install distribution conduit in segments within the parcel.
Please note, construction activities are subject to change due to weather or unexpected circumstances.
Work hours remain 7 PM - 5 AM during working days. Some work may be conducted beyond normal work hours with approval from city officials.
There will be no work on Monday, April 17.
Residents may reach out to Outreach Specialists Matt Watkins at matthew.watkins@eversource.com or 617-571-4582 and Eric Sacchetti at eric.sacchetti@eversource.com or 781-570-1228 with any questions or concerns.