Planned Activities for the Week of 1/16/2023 - 1/22/2023

10 Prospect Street (D2.1) – Future Life Sciences Building (closest to Somerville Avenue)
Gilbane Building Company
The following activities are expected to take place:

  • Somerville Ave Sidewalk installation

  • Curtain wall deliveries and installation with a crane and a lull on the first floor

  • Masonry walls on the first floor

  • Elevator installation

  • Interior fit out of the core

  • Mechanical room fit out

  • Electrical room rough in

Weekend Work (1/14): Envelope installation and interior fit out will be completed.


20-50 Prospect Street (D2.2-D2.3) – Future Apartment Building (closest to MBTA Station)
Cranshaw Construction
The following activities are expected to take place:

  • Façade & sealant work at the tower & midrise

  • Wood parapet work at the midrise

  • MEP rough at the tower & midrise

  • Interior framing & drywall at the tower & midrise

  • Interior finishes at the tower & midrise

  • Roof work at the tower & midrise

  • Masonry shaft block work at the garage

Weekend Work (1/14): MEP rough, drywall work and trash removal operations at the tower and midrise.   

Eversource Neighborhood Infrastructure Project - Work Performed 7PM to 5AM
Update provided by Eversource: 

  • Eversource approved contractors will continue to perform construction activities within the parcel.

  • Crews will perform construction related to the testing and relocation of water main infrastructure. Residents should not expect an interruption to their water service.

  • Work hours remain 7 PM - 5 AM during working days.

For any questions or concerns, residents can reach Keith Sonia, Public Outreach Manager at Eversource. Phone: 781-720-9726; E-Mail: keith.sonia@eversource.com.

Previous
Previous

Planned Activities for the Week of 1/23/2023 - 1/29/2023

Next
Next

Planned Activities for the Week of 1/9/2023 - 1/15/2023