Planned Activities for the Week of 11/21/2022 - 11/27/2022

10 Prospect Street (D2.1) – Future Life Sciences Building (closest to Somerville Avenue)
Gilbane Building Company
The following activities are expected to take place:

  • Somerville Ave Sidewalk installation

  • Curtain wall deliveries and installation with a crane

  • Masonry walls on the first floor

  • Elevator installation

  • Interior fit out of the core

  • Mechanical room fit out

  • Electrical room rough in

Note: There is no work scheduled on Saturday, 11/19. 

20-50 Prospect Street (D2.2-D2.3) – Future Apartment Building (closest to MBTA Station)
Cranshaw Construction
The following activities are expected to take place:

  • Façade & sealant work at the tower & midrise

  • Wood panel erection at the midrise

  • MEP rough at the tower & midrise

  • Interior framing & drywall at the tower & midrise

  • Finish work at the tower

  • Roof work at the tower & midrise

  • Masonry shaft block work at the garage

Weekend Work (11/19): Trash removal operations, MEP rough & facade work at the tower & midrise.

Eversource Neighborhood Infrastructure Project - Work Performed 7PM to 6AM
Update provided by Eversource: 

  • Eversource approved contractors are continuing a period of data analysis to guide upcoming construction efforts.

  • In advance of future work, crews may mobilize dewatering equipment to the site.

  • As part of the above, residents can expect crews to perform minor surveying work during working hours. Residents can also expect the site to be well-lit during working hours; noise will largely be relegated to that of vehicles delivering essential equipment.

  • Work hours remain 7:00 PM - 6:00 AM.

For any questions or concerns, residents can reach Keith Sonia, Public Outreach Manager at Eversource. Phone: 781-720-9726; E-Mail: keith.sonia@eversource.com.